Ward 7 & 8 Senior Wellness Center Upgrades

Project Name

Ward 7 & 8 Senior Wellness Center Upgrades

Project Location

3001 Alabama Ave SE & 3500 Martin Luther King Jr. Ave SE, Washington, DC

Project Start/Completion

8/01/2019 to 3/15/2020

Scope of Work

Senior Wellness Center Upgrades

Project Size

18,500 SF

Agency/Municipality

DGS

Contract Amount

$ 1,351,000.00

Project Narrative

  • The work for this project was selective interior and exterior demolition and finish upgrades. The site was not occupied during construction activities.
  • The delivery method for this contract was CM at Risk method. The work was issued via a prime contract, 50% of the project was subcontracted to CBEs.
  • The start and end dates for construction were August 2019 and March 2020, the project was delivered on time.
  • The self-performed trades were HVAC upgrade, demolition, framing, paint and acoustical ceiling tile.
  • The date and point during design DC General was engaged was in May 2019.
  • The initial substantial completion date for the contract was December 31, 2019. The initial contract value was $1,351,000.00.
  • The level of completion of design documents initial contract was based on is 100% construction documents.
  • The actual substantial completion date for the contract was March 30, 2020. The final contract value was $1,351,000.00.