Project Narrative
- The work for this project was design-build of 100-unit luxury condominiums
- The delivery method for this contract is the Design-Build method, 40% of the project was subcontracted to CBEs.
- The start and end dates for this contract were August 2019 and January 2022, the project was delivered on time.
- The self-performed trades for this contract were demolition and framing.
- The date and point during design DC General was engaged was in December 2018, during schematic design phase.
- The initial substantial completion date for the contract was January 2022. The initial contract value was $52,500,000.
- The level of completion of design documents initial contract was based on is based on is 100% construction documents.
- The actual substantial completion date for the contract was January 2022. The final contract value was $54,000,000.