Congress Heights Senior Wellness Center Addition

Project Name

Congress Heights Senior Wellness Center Addition

Project Location

3500 MLK Jr. Ave. SE, Washington DC 20032

Project Start/Completion

8/29/2022 to 2/28/2023

Scope of Work

New Addition Building

Project Size

3,680 SF

Agency/Municipality

DGS

Contract Amount

$ 794,911.00

Project Narrative

  • The work for this project included a new addition to the existing Congress Heights Senior Wellness Center building. This new construction included, foundation, slab-on-grade, structural and cold form framing, new roofing work and interior finishes. The site was occupied during construction activities.
  • The delivery method for this contract is the lump sum method. The work is issued via a task order contract, 50% of the project was subcontracted to CBEs.
  • The start and end dates for construction were August 2022 and February 2023, the project will be delivered on time.
  • The self-performed trade for this contract was rough carpentry.
  • The initial substantial completion date for the contract was December 31, 2022. The initial contract value was $794,911.00.
  • The level of completion of design documents initial contract was based on is 100% construction documents.
  • The actual substantial completion date for the contract will be February 28, 2023. The final contract value is to be determined.